Home > Tuas Power Station > Stage I
Font size  [ + ]   [ - ]
Stage I
Key Design Features  |  Plant Process Overview

Construction of Stage I Tuas Power Station, comprising two 600 MW fuel-oil fired steam units, began in November 1994. The first 600 MW unit of Stage I was in commercial operation in March 1999 while the second unit was taken over in December 1999.





Key Design Features


  • Comprehensive back-up for critical equipment so that a single failure will not cause the generating unit to trip
  • Unitised design concept in which critical equipment are not shared between generating units, to minimise the impact of equipment failure
  • Steam-turbine-driven boiler feedwater pumps to improve plant efficiency
  • 40% turbine bypass system permits fast hot-start and operational flexibility


Plant Process Overview

Fuel oil is delivered by large oil tankers at the plant's jetty, via two unloading arms, each with a capacity of 2,000 tonnes per hour. The fuel oil is then transferred to six fuel oil storage tanks before being transferred to two day oil tanks.

Fuel is then delivered from the day oil tank to the boiler where the combustion process takes place. This process will generate hot gas that will heat the water and steam inside the boiler tubes.

The superheated steam is then allowed to flow through the main steam pipe to the turbine. The steam impinges on specially shaped blades of the turbine and causes the turbine to turn at high speed. A two-pole synchronous generator is employed to convert mechanical energy from the turbine to electrical energy.